IGT064 – Removal of Ancillary Document Self-Governance

This Modification was raised by ESP on 5th June 2014.

The Panel of 18th June 2014 agreed to circulate the Proposal for DMR consultation.

The DMR was circulated on 20th June 2014 closed on 11th July 2014.

The FMR was circulated on 25th July 2014 and considered by the Modification Panel on 20th August 2014.

The Modification Panel recommended implementation of the Modification with a two month implementation lead time.

The FMR was sent for Authority Decision on 21st August 2014. The Authority Decision to implement was received on 19th September 2014.

IGT064 will be implemented on 27th February 2015.

Document Title Description Type Pub Date Author
IGT064 Authority Decision Adobe PDF 19/09/2014  
IGT064 Final Modification Report to Ofgem Adobe PDF 21/08/2014  
IGT064 Final Modification Report Adobe PDF 25/07/2014  
npower DMR Response Adobe PDF 14/07/2014  
SSE Supply DMR Response Adobe PDF 14/07/2014  
E.ON DMR Response Adobe PDF 14/07/2014  
British Gas DMR Response Adobe PDF 14/07/2014  
IGT064 Draft Modification Report Adobe PDF 20/06/2014  
IGT064 Modification Proposal Adobe PDF 05/06/2014