IGT089 – Revision to the Modification Rules in Response to CGR3 – Self Governance

  • Raised by ES Pipelines on 10th August 2016
  • Panel consideration on 17th August 2016
  • Work Group concluded 6th September 2016
  • Panel considered Work Group report on 21st September 2016
  • Draft Modification Report published 23rd September 2016
  • DMR consultation closes 14th October 2016
  • Consultation responses published 17th October 2016
  • Final Modification Report (Pre Panel) published 18th October 2016
  • Panel Decision 16th November 2016
  • Final Modification Report (Post Panel) Published 18th November 2016
  • The Panel accepted the Final Modification Report on 18th November, with all parties supporting the Implementation.
  • IGT089 is to be implemented on the 23rd February 2017 IGT UNC Code release.
Document Title Description Type Pub Date Author
IGT089 Notice of Implementation Adobe PDF 01/12/2016 Code Administrator
IGT089 Final Modification Report (Post Panel) Adobe PDF 18/11/2016 Code Administrator
IGT089 Final Modification Report (Pre Panel) Adobe PDF 18/10/2016 Code Administrator
IGT089 DMR Consultation Responses ZIP Zip Archive 18/10/2016 Code Administrator
IGT089 DMR Consultation Response Adobe PDF 17/10/2016 Scottish Power
IGT089 DMR Consultation Response Adobe PDF 17/10/2016 E-ON
IGT089 DMR Consultation Response Adobe PDF 17/10/2016 SSE Supply
IGT089 Draft Modification Report Adobe PDF 23/09/2016 Code Administrator
IGT089 Workgroup Report Adobe PDF 14/09/2016 Code Administrator
IGT089 Initial Modification Proposal Adobe PDF 10/08/2016 Code Administrator