IGT042 EU 3rd Package – 21 day switching with flexible objection period

The Modification was raised by SSE on the 9th November 2011.

The Modification has been directed for Development.

The Development Group was led by Cher Harris (SSE Pipelines). After several meetings, the Development Group submitted a Report to the February 2012 Modification Panel. The Panel agreed that both IGT041 and IGT042 should proceed to the Draft Modification Report stage and be issued with reduced consultation timeframes. This would enable to Modifications to be submitted to Ofgem in alignment with the equivalent UNC Modifications.

The Draft Modification Report (DMR) was published on the 7th March and considered at the Modification Panel on the 21st March 2012.

The Final Modification Report (FMR) was published and sent to Ofgem on the 27th March 2012.

Ofgem have released their decision on this modification, which can be found below.

Implementation of this Modification Proposal has now been confirmed as 1st November 2013 – in line with the UNC Mod 0403.

Document Title Description Type Pub Date Author
IGT042 Authority Decision Adobe PDF 03/09/2012  
IGT042 Final Modification Report Adobe PDF 27/03/2012  
IGT042 Draft Final Modification Report Adobe PDF 07/03/2012  
IGT042 DMR Consultation Responses Zip Archive 07/03/2012  
IGT042 Draft Modification Report (21st Feb) Adobe PDF 21/02/2012  
IGT042 Draft Modification Report (Superseded – published for information purposes only) Adobe PDF 17/02/2012  
IGT042 Modification Proposal Adobe PDF 09/11/2011